Inert Gas Generator
Design features & Operational procedure
- Operation based on the combustion of a low sulphur content file and the cleaning and drying of the exhaust gases
- Good combustion is essential
- Oxygen level controls the ratio of the air / fuel to the burner
- IG plant includes an inert gas generator, a scrubbing tower unit, two combustion-air blower,
- An effluent water seal, a fuel injection unit, an intermediate dryer unit (refrigeration type), a final dryer unit, and an instrumentation/control system
- Dry air/inert gas plant operation local and fully auto control mode
- Demister for water droplets and trapped moisture
- Freon dryer unit reduces dew point to 5 deg.C
- Absorption dryer-dual vessel desiccant dryer reduces dew point further
- Pressure control valve at the outlet of the dryer unit maintains constant pressure throughout the system, thus ensuring a stable flame at the generator
- Dew point and oxygen content of the inert gas produced are permanently monitored.
- Purge valve and the deliver valve-fail safe solenoid operated acting in reverse direction
- Connection to the cargo piping system through two non-return valves and a spool piece
1.Preparations starting
- Operation schedule and procedure is determined and coordinated with persons in the engine room, CCR and deck
- Lubrication of all running machinery ensured
- Manual operational check of all system valves
- Power for operating equipments to be switched on
2.Inerting mode
- Pre purge operation to be confirmed
- Purge air and IG for predetermined interval after start is vented out
- Automatic ignition and main burner operation as per the automatic operation program to be verified wajar
- Atomizing steam pressure via special super heater in the combustion chamber
- Oxygen content adjustment done and maintain the combustion condition-Flame colour through peep hole good indicator
- Absorbent type dryer and the refrigerating dryer put into operation
- Confirm that the operating parameters of each part are normal
- Main supply to deck start after dew-point temperature and the oxygen content is as per the set point and stable
3.Stopping
- Main selector valve from the tank or the hold change over to atmosphere
- Stop the adsorbent dryer and the refrigerating dryer as per the instructions
- Confirm that predetermined operation takes as per the programmed stop sequence. Ensure post purge and fuel cut off for IG mode
- Fuel to the burner cut off and the post-purge operation to be verified